Dear Strawbridge family:
Following approval at the Church Conference last October, our project to build a new
education building and renovate the existing children’s area is moving ahead as planned:
- As of year-end 2024, over $1.44 million of the total $3.35 million dollars of pledges have been received – the support of the congregation is much appreciated
- Detailed construction drawings and specifications will be completed in February and we will immediately move into a 4 to 6 month permitting exercise
- We anticipate having an updated cost estimate and financing arranged by mid-March, after which final reviews with the Church Council/Charge Conference will be completed prior to executing the construction contract and financial documents
- Re-roofing of existing buildings and renovation of the choir room are planned over this summer
- Ground-breaking for the new building is planned in September 2025, with occupancy in early-May 2026 prior to starting the renovation work
- Renovation of the children’s area will start in mid-May 2026 for completion in September 2026, though our Bright Beginnings Learning Center (BBLC) will be able to occupy enough space to start the 2026 fall semester in mid- to late-August by temporarily placing 3 classrooms in the new building
We look forward to fulfilling this phase of our vision to support our ministries and
missions – sufficient adult Sunday School space, a dedicated nursery and improved security for our children’s area, more storage areas for missions, safer choir risers, and new roofs. Architectural and Engineering Committee Chair, Bill Koerner, will be happy to answer any questions you may have. You can email Bill here.
Peace and blessings,
The Embrace the Spirit Team
Strawbridge UMC
|