PROJECT UPDATE
Walker Road phase 2

July 2024

Recently completed work:


  • Installed traffic signals and removed old poles and mast arms on Walker Road at 158th Avenue, Greystone Court, 150th Avenue, and Meadow Drive.
  • Installed retaining walls along the Fred Meyer/Les Schwab frontage, both along 158th Avenue and Walker Road.
  • Installed new storm pipe and structures between 150th Avenue and Butner Road.
  • Constructed a new temporary THPRD access off Walker Road (access will still be limited to right-in/right-out only).
  • Continued installation of new light poles, bases, and conduits along the north side of Walker Road, between 158th Avenue and Butner Road.
Walker Road phase 2

Upcoming work:


Today and Tomorrow (July 11-12): Temporary signal shutdowns to allow for the transfer from temporary power to permanent power connection. One intersection will be down at a time and the intersection will be flagged.


  • Week of July 15: Paving along the north side of Walker Road as follows:
  • Monday, July 15: Paving between Schendel and 150th avenues, temporarily closing both Fred Meyer’s Walker Road driveways, as well as THPRD’s Walker Road access for the day.
  • Tuesday, July 16: Paving the west side of 158th Avenue and new multi-use path along THPRD's Walker Road frontage, temporarily closing Fred Meyer’s 158th access and THPRD’s Walker Road access for the day.
  • Wednesday, July 17: Pave north side of Walker from 150th to Butner, pave a portion of 150th. 
  • Thursday, July 18: Pave remainder of 150th Avenue.
  • Friday July 19th: Apply temporary striping to street in preparation of traffic changes.
  • Week of July 22: Begin flipping construction work zone to the south side of Walker and through-traffic to north side of Walker Road.
  • Week of Aug. 12:
  • Begin vegetation removal along south side of Walker Road.
  • Continue installing sidewalks and ramps along north side of Walker Road and west side of 158th Avenue.
  • Continue installing conduit, junction boxes and light pole bases along north side of Walker Road, between Meadow Drive and Butner Road.



Visit wc-roads.com for more traffic updates.

Walker Road phase 2

Traffic impacts:


Rolling temporary signal shutdowns are scheduled on Walker Road today (July 11) and Friday (July 12) for permanent power connections for new traffic signals.


Upcoming Traffic Changes:


Construction activities will move to the south side of Walker Road the week of July 22 with through-traffic being moved to the newly constructed north side. This traffic switch will include the relocation of concrete traffic barriers and the temporary restriping on Walker Road.


Drivers:


Current traffic for westbound Walker Road, through the work area, is still reduced to one lane between Murray Boulevard and 158the Avenue.


Pedestrians:


Sidewalks remain closed along the north side of Walker Road. Once the construction operations have been moved to the south side, the sidewalks along the south side of Walker will be closed and pedestrians will be directed to use the new sidewalk along the north side of Walker Road through the work zones.


Cyclists:


The westbound bike lane on the north side of Walker Road has been relocated adjacent to the concrete barriers. This lane will be restored once the construction operations have switched to the south side.

 

Transit:


All stops for Routes 67 (Bethany/158th) and 59 (Walker/Park Way) are open though there may be temporary disruptions to stops due to current construction activities. Route 67 (Stop ID #6832) adjacent to Tualatin Hills Howard Terpenning Complex has been restored and is now open.



Visit wc-roads.com for more traffic updates.

Walker Road phase 2

Thank you for slowing down in work areas!


As with all construction projects, we apologize for the temporary inconvenience and appreciate your patience and understanding.


Read about completed and up-coming work below.