At the last CMS Building Committee meeting, the Committee accepted the recommended contractors and the construction costs as presented by the Construction Manager. The total construction cost accepted is $58.6 million for the middle school and central administration building. The total project budget is $72.6 million which includes the construction costs, soft costs and furniture & fixtures. At this time the project is tracking $3.9 million under budget. Cromwell's reimbursement rate from the state is 49.96%. There will be items noted as ineligible for state reimbursement in the final review. The project’s construction is scheduled to begin Feb. 15. We will celebrate the milestone with a groundbreaking ceremony on Feb. 21 from 4:30 to 5 p.m. at CMS.
Construction is scheduled to begin February 15.
Upcoming Meetings
Wednesday, February 7, 7:00 pm Virtual
Wednesday, February 21, 7:00 pm Virtual
Stay up to date with the project! All meeting videos, agendas and minutes are included on the committee’s website.