495 NEXT Project

Lane Closures and Traffic Changes

August 21 - 25, 2023

The following construction-related lane closures and traffic changes are planned to occur in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers should expect potential delays when traveling in this area, and are encouraged to visit 511virginia.org for current information on travel conditions and work zones in Virginia. All construction-related work and closures are subject to change based on weather and other factors.

Upcoming Highlights

  • Daytime and nighttime single lane closures on Georgetown Pike.
  • Daytime and nighttime single lane closures on I-495 North and South.
  • Daytime flagging operations on Balls Hill Road and Live Oak Drive.
  • Daytime single lane closures on westbound Dulles Toll Road and westbound Dulles Access Road.

Lane Closures 

I-495 (CAPITAL BELTWAY)


I-495 North


Monday, August 21, through Thursday, August 24, 10 a.m. to 3 p.m.

Single right lane closures on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for excavation, pipe, erosion, and sound wall retaining work.


Monday, August 21, through Friday, August 25, 10 a.m. to 3 p.m. and 9:30 p.m. to 5 a.m.

Alternating single mobile lane closures on northbound I-495 throughout the project corridor for traffic maintenance.


I-495 South


Monday, August 4, through Thursday, August 17, 9:30 a.m. to 2:30 p.m.

Single right lane closures on southbound I-495 between Georgetown Pike and Dulles Toll Road for drainage, erosion, bridge, embankment, and sound wall retaining work.


Monday, August 14, through Thursday, August 17, 9:30 a.m. to 2:30 p.m. and 9:30 p.m. to 5 a.m.

Alternating single mobile lane closures on southbound I-495 throughout the project corridor for traffic maintenance.

LIVE OAK DRIVE


Monday, August 21, through Friday, August 25, 9 a.m. to 3:30 p.m.

Live Oak Drive will be reduced to a single lane to accommodate water line work and saw cutting. Flagging operations alternating single traffic lanes will be in effect.

BALLS HILL ROAD


Monday, August 21, through Friday, August 25, 9 a.m. to 3:30 p.m.

Balls Hill Road will be reduced to a single lane at the Live Oak Drive intersection to accommodate water line work. Flagging operations alternating single traffic lanes will be in effect.

GEORGETOWN PIKE INTERCHANGE


Monday, August 21, through Friday, August 25, 9:30 a.m. to 3 p.m. and 10 p.m. to 5 a.m.

Single lane closures on east- and westbound Georgetown Pike as needed for traffic signal work.

DULLES CORRIDOR INTERCHANGE 


Dulles Toll Road


Monday, August 21, through Thursday, August 24, 9:30 a.m. to 3 p.m.

Single right lane closure westbound Dulles Toll Road (267 Connector) between Route 123 and the I-495 interchange for pipe, embankment, and bridge work.


Dulles Access Road


Monday, August 21, and Tuesday, August 22, 9:30 p.m. to 5 a.m.

Single right lane closure on westbound Dulles Access Road between Route 123 and the I-495 interchange for guard rail removal.

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange. Learn more about the traffic change here.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project. Learn more about the traffic change here.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scotts Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

mainphoto1722.png

Learn More About the Project


Check out www.495NEXT.org for additional information.


Sign up to receive project email updates.



laptop_495EX website.png

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461