WHAT:
Southern California Edison (SCE) is scheduled to install new power lines across all lanes of SR-55.
This work will require a full closure of northbound and southbound SR-55 between Edinger Avenue and Dyer Road, as well as westbound Warner Avenue over SR-55.
Crews may need to return the following weekend to complete the work.
WHEN:
Northbound and southbound SR-55 as early as 10 p.m. to 5 a.m. nightly, Friday, April 26 and Saturday, April 27.
Tentative Closure: Southbound SR-55 between Edinger Avenue and Dyer Road from 10 p.m. to 5 a.m. nightly, Friday, May 3 and Saturday, May 4.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
|