495logo.jpg

495 NEXT Project

Lane Closures and Traffic Changes

July 17 - 22, 2023

The following construction-related lane closures and traffic changes are planned to occur in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers should expect potential delays when traveling in this area, and are encouraged to visit 511virginia.org for current information on travel conditions and work zones in Virginia. All construction-related work and closures are subject to change based on weather and other factors.

Upcoming Highlights

  • Daytime single and nighttime multi-lane closures on I-495 North and South
  • Daytime single lane closures at the Georgetown Pike interchange
  • Daytime flagging operations on Balls Hill Road, Old Dominion Drive and Lewinsville Road
  • Daytime single lane closures on westbound Dulles Toll Road
  • Advance Notice: Wednesday, August 2, 11 p.m. to 4 a.m., the ramp from southbound I-495 to eastbound George Washington Memorial Parkway (exit 43) will be closed and a detour will be in place

Lane Closures 

I-495 (CAPITAL BELTWAY)


I-495 North


Monday, July 17, through Thursday, July 20, 10 a.m. to 3 p.m.

Single right lane closures on northbound I-495 between Lewinsville Road and Georgetown Pike.


Monday, July 17, through Thursday, July 20, 11 p.m. to 5 a.m.

Triple left lane (Mon. and Tues.) and double right lane (Wed. and Thurs.) closures on northbound I-495 between Old Dominion Drive and George Washington Memorial Parkway for bridge work.


Monday, July 17, through Friday, July 21, 10 a.m. to 3 p.m.

Mobile lane closures on northbound I-495 throughout the project corridor for mowing, weed clearing, and litter pickup.


I-495 South


Monday, July 17, through Thursday, July 20, 9:30 a.m. to 2:30 p.m.

Single right lane closures on southbound I-495 between Georgetown Pike and Dulles Toll Road for bridge work.


Monday, July 17, through Friday, July 21, 9:30 a.m. to 2:30 p.m.

Mobile lane closures on southbound I-495 throughout the project corridor for mowing, weed clearing, and litter pickup.


Friday, July 21, 10 p.m. to 7 a.m.

Triple left lane closure on southbound I-495 between George Washington Memorial Parkway and Old Dominion Drive for bridge work.


Saturday, July 22, 10 p.m. to 9 a.m.

Single lane closures on southbound I-495 and on the southbound I-495 collector-distributor road (exits 43 and 44) between George Washington Memorial Parkway and Old Dominion Drive for bridge work.

LIVE OAK DRIVE


Monday, July 17, through Friday, July 21, 7 a.m. to 3 p.m.

The rear exit of the Langley Swim and Tennis club will be closed for tree clearing operations.

BALLS HILL ROAD


Monday, July 17, through Friday, July 21, 9 a.m. to 3:30 p.m.

Balls Hill Road will be reduced to a single lane at the Live Oak Drive intersection to accommodate water line installation. Flagging operations alternating single traffic lanes will be in effect.

GEORGETOWN PIKE INTERCHANGE


Monday, July 17, through Friday, July 21, 9:30 a.m. to 3 p.m.

Single left lane closure on the onramp from Georgetown Pike to northbound I-495 for bridge work. The left turn lane on eastbound Georgetown Pike on the bridge will also be closed at this time.

OLD DOMINION DRIVE


Monday, July 17, through Friday, July 21, 9:30 a.m. to 3 p.m.

Old Dominion Drive will be reduced to a single lane to accommodate clearing and bridge work. Flagging operations alternating single traffic lanes will be in effect on Old Dominion Drive on the east side of the bridge over I-495.

LEWINSVILLE ROAD


Monday, July 17, through Friday, July 21, 9:30 a.m. to 3 p.m.

Lewinsville Road will be reduced to a single lane to accommodate drainage and concrete joint work. Flagging operations alternating single traffic lanes will be in effect.

DULLES CORRIDOR INTERCHANGE 


Dulles Toll Road


Monday, July 27, through Thursday, July 20, 9:30 a.m. to 3 p.m.

Single left lane closure on westbound Dulles Toll Road (267 Connector) between Route 123 and the I-495 interchange for bridge work.

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange. Learn more about the traffic change here.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project. Learn more about the traffic change here.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scotts Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

mainphoto1722.png

Learn More About the Project


Check out www.495NEXT.org for additional information.


Sign up to receive project email updates.



laptop_495EX website.png

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461