I-495 (CAPITAL BELTWAY)
I-495 North
Monday, November 6, through Thursday, November 9, 10 a.m. to 3 p.m.
Single right lane closure on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for drainage, sound wall, embankment, and excavation work.
Monday, November 6, through Friday, November 10, 9:30 p.m. to 5 a.m.
Alternating single mobile lane closures on northbound I-495 throughout the project corridor as needed for maintenance work and traffic management.
Friday, November 10, 10 a.m. to 3 p.m.
Alternating single mobile lane closures on northbound I-495 throughout the project corridor as needed for maintenance work and traffic management.
I-495 South
Monday, November 6, through Thursday, November 9, 9:30 a.m. to 2:30 p.m.
Single right lane closure on southbound I-495 between Georgetown Pike and Dulles Toll Road for drainage, excavation, embankment, and sound wall work.
Monday, November 6, Tuesday, November 7, and Thursday, November 9, 9:30 p.m. to 5 a.m.
Double right lane closures on southbound I-495 at the Scott's Run bridge for demolition work and overhead sign removal.
Monday, November 6, through Friday, November 10, 9:30 p.m. to 5 a.m.
Alternating single mobile lane closures on southbound I-495 throughout the project corridor as needed for maintenance work and traffic management.
Wednesday, November 8, through Thursday, November 9, 9:30 a.m. to 2:30 p.m.
Single left lane closure on the ramp from southbound I-495 to Georgetown Pike for construction entrance work.
Thursday, November 9, 9:30 p.m. to 5 a.m.
Single right lane closure on the southbound collector/distributor road exit to George Washington Memorial Parkway (exit 43) for overhead sign removal. There may be brief total traffic stoppages during this time.
Friday, November 10, 9:30 a.m. to 3 p.m.
Alternating single mobile lane closures on southbound I-495 throughout the project corridor as needed for maintenance work and traffic management.
|