SHARE:  

Construction Update

Colchester Exit 17 Project

Colchester NH 028-1(31)

DATE: Friday, August 16, 2024

TRAFFIC IMPACT AND DURATION: From Monday, August 19, through Friday, August 23, between 9 a.m. and 3 p.m., there will be alternating one-way traffic controlled by flaggers on U.S. Route 7 (U.S. 7) between the Shell Gas Station and Wiley Road and U.S. Route 2 (U.S. 2) between the bridge over Interstate 89 (I-89) and Jasper Mine Road.


I-89 will be reduced to a single lane in both directions near Exit 17. The single-lane closures will occur during off-peak hours: 6 a.m. to 3 p.m. on I-89 northbound and 9 a.m. to 8 p.m. on I-89 southbound, with an intermittent lane width reduction on the northbound off-ramp.


On Monday, August 19, southbound traffic on Interstate 89 exiting at Exit 17 will permanently shift to the new southbound off-ramp located west of the existing off-ramp. A supplemental Traffic Alert will follow.


Motorists are advised to slow down and use caution while traveling through the work zone. Delays along U.S. 7 and U.S. 2 are expected; please allow additional travel time through the area.  

CONSTRUCTION ACTIVITIES: Crews plan to pave U.S. 7 between the Shell Gas Station and Wiley Road. There is potential for excavation along U.S. 2 between the bridge over I-89 and Jasper Mine Road.


Crews will continue driving piles for the new U.S. 2 bridge over I-89, with work performed adjacent to the I-89 northbound and southbound lanes.


Crews will install geotechnical instruments to monitor the construction of the U.S. 2 bridge near the I-89 northbound off-ramp.

Crews continue driving piles for the new U.S. 2 bridge over I-89

in Colchester, VT.

LOCATION: The segment of U.S. 2, starting just east of Jasper Mine Road and extending just under a half mile east to its intersection with U.S. 7 at Chimney Corners. The segment of U.S. 7, starting just south of the Shell Gas Station/Simon’s Chimney Corner Store and extending just over a half mile north to its intersection with Wiley Road. The Exit 17 interstate ramps and the portion of I-89 bounded by them. 

PROJECT COMPLETION: Summer 2026

Project Website
Project Factsheet

CONTACT US:

24-Hour Project Hotline: 802-595-4399

Project Email: info@ColchesterExit17.com

The Colchester Exit 17 Project will be completed in six phases over three construction seasons, beginning in Spring 2024 and continuing through Summer 2026.

Sign Up for Project Email Updates