Construction Update
Exit 16 DDI
DATE: Friday, September 15, 2023
TRAFFIC IMPACT AND DURATION:
Monday, September 18, through Friday, September 22, during the daytime hours, 6:00 a.m. – 3:00 p.m., the outermost southbound lane and the outermost northbound lane of U.S. 2/7 between South Park Drive and Mountain View Drive will be closed. Only a single travel lane will be closed in each direction during the daytime hours. Intermittent lane width reductions will be in effect along the Interstate 89 (I-89) northbound onramp. Interstate ramp access and side streets will be maintained throughout this work. Motorists are strongly encouraged to use caution while driving through the work zone and pay close attention to signage as traffic patterns will change. All users should expect delays and plan ahead.
CONSTRUCTION ACTIVITIES: 
Next week, during daytime hours, crews will work along the west side of U.S. 2/7 between South Park Drive and Mountain View Drive conducting shaping work, installing curb near Whitcomb Street, and removing the remaining ledge near the I-89 northbound onramp under single lane closure and lane width reductions. In addition, crews will install sidewalk along the east side of U.S. 2/7 near its intersection with South Park Drive in the vicinity of McDonald's under a single lane closure. 
Crews completed the installation of the retaining wall
along the west side of U.S. 2/7. 
LOCATION: U.S. Routes 2/7 (U.S. 2/7) in Colchester starting at the Winooski town line and continuing north for 1.05 miles to Sunderland Woods Road.

PROJECTED COMPLETION: Contract 1 Spring 2024 / Contract 2 Summer 2026
Diverging Diamond Interchange Comes to Vermont Educational Video
This video provides an overview of the Exit 16 DDI project, discusses the benefits of the Diverging Diamond Interchange design, and demonstrates how drivers, cyclists and pedestrians will navigate the new traffic pattern coming to Colchester, VT.

Translated Materials
VTrans is committed to providing a comprehensive and robust communications and public outreach program as part of this project. 

The project website has been upgraded to include a translation feature with the ability to automatically translate website content into 11 languages. 

In addition, the website is now home to a translated materials tab which includes several frequently asked questions and answers that have been translated into 11 languages with help from trained interpreters and translators from AALV in Burlington, Vermont. 

Contact Us!

24 Hour Project Hotline - 802-595-4399


Want to join our mailing list? Send us an email!
To learn more about VTrans Construction Projects, visit our projects website.