Construction Activity

Nighttime alternating lane closures along

eastbound I-10 scheduled tonight!

Friday, August 11

7 p.m. - 5 a.m.

Week of August 14, 2023


  • Earthwork, drainage, and minor concrete improvements continue in the center median and roadway shoulders


  • Rebar installation and concrete pours continue at several bridge locations


  • Asphalt and concrete paving along eastbound I-10 scheduled to begin early-Fall

Upcoming Closures

Starting in late-August, eastbound and westbound I-10 Cactus City rest areas will be fully closed for utility work. Additional information, including the full duration of the closure will be shared at a later date. For additional project updates, visit I10DesertRehab.com.

Project Updates
Get the Latest Travel Updates
Download the Caltrans QuickMap to get real-time traffic updates including lane closures, roadway conditions, traffic speeds, and more! Click here to download the app today!
Project Background
The I-10 Desert Rehab Project segment is a 13-mile stretch of the I-10 freeway near Coachella in Riverside County, between 1.8 miles east of the Dillon Road Interchange and 2 miles east of the Cactus City Rest Area. Construction will take place over the next 3.5 years and includes repaving I-10, updating lane striping, and the addition of an eastbound truck climbing lane. The Cactus City Rest Area will also be closed for 1-2 months during construction. 

In addition to repairing and restoring existing roadway pavement and adding an eastbound truck climbing lane, the I-10 Desert Rehab Project will install electric vehicle charging stations at the Cactus City Rest Area, replace and upgrade bridge railings, guardrail systems, and roadway signage, and improve roadway infrastructure including drainage and stormwater treatment systems.
Neighboring Projects
Click here for more information on the I-10 Tune Up Project
Click here for more information on the I-10 Blythe Pavement Rehabilitation Project