3 Week Charlotte Street Outlook

Week of July 31


Working: Greeley to Jay

Crews will:

  • Prepare subgrade for concrete installation. 
  • Install curb and gutter north and south sides.


Working: Estes to Columbine

  • Crews will start the waterline installation.

Week of August 7


Working: Greeley to Jay

  • Crews will start concrete ADA installations


Working: Estes to Columbine

  • Crews will continue the waterline installation

Week of August 14


Working: Greeley to Jay

  • Crews will start roadway excavation and prep for asphalt paving.


Working: Estes to Columbine

  • Crews will begin pressure and BacT testing for the waterline and then start the water service lines.

During construction in this segment the contractor will be moving trash cans to a location for the solid waste trucks to pick up all of the trash and recycling for the residents and then moving the cans back to their home locations. Access is accommodated through the alleyways behind the homes. 


Crews will be occasionally working occasional Saturdays from 8 am - 4 pm to help with catch up from weather delays that have occurred.

 

Visit johnstownco.gov/CharlotteSt2023 for more information