Construction Activities


In observance of Labor Day, there will be no closures scheduled Friday, Sept. 1 through Monday, Sept. 4.


Bridge Work


Crews are making progress on the MacArthur Boulevard and Edinger Avenue bridges, which were demolished earlier this year.


A nighttime concrete pour is expected to occur on Thursday, Sept. 7 at the MacArthur Boulevard bridge followed by rebar work to begin in mid-September. MacArthur access will be maintained. Meanwhile, crews are also expected to excavate the for the bridge columns at Edinger Avenue before placing concrete piles that will support the bridge.

Retaining Walls


More than a half-dozen retaining walls are being constructed and are in different stages of construction. Activities may include excavation, steel placement, wall forming, and nighttime concrete pours.


Contractors are expected to begin preparations to demolish the existing retaining wall and build a new retaining wall along Hutton Centre Drive, south of MacArthur Boulevard (pictured below). Contractors are expected to remove portions of roadway. Subsequently, crews will shift to night work to install a shoring system, followed by demolition of the existing retaining wall. Additional information will be provided once this work is scheduled.

In the Community

On Saturday, Sept. 9 from 11 a.m. to 3 p.m. the SR-55 Public Outreach team will be hosting a Project booth at the 26th Annual Tustin PD Open House. This free family-friendly event features games, food and demonstrations by motorcycle officers, the K-9 unit, SWAT team and more!


Stop by our booth to learn about construction activities and sign-up for project updates. We look forward to seeing you there! Visit www.tustinca.org/police for more information.

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

Business Spotlight: AGL Grass West

This week's Focus on 55 business spotlight is AGL Grass West. AGL Grass West strives to deliver first-class service to all contractors, architects, and developers. They supply the most innovative, best-in-class synthetic grass for installation, distributing from Beverly Hills to Escondido, Palm Springs, Laguna Beach, the Newport Coast, and those along the way. 



1392 McGaw Avenue, Irvine, CA 92614

833-424-5472

sales@aglgrasswest.com

https://aglgrass.com


To learn more about OCTA's Focus on 55 Program, including official rules and eligibility, visit octa.net/Focuson55 or click here to enroll your business today.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.

Stay Connected-01.png