Next week's work schedule
Monday, July 24 to Tuesday, July 25
Wednesday, July 26 to Friday, July 28
- Deliver excavation equipment to the site;
- Receive delivery of concrete sewer maintenance holes;
- Conduct utility layout with surveying and paint markings;
- Dig test pits on Smith Well Road.
Residents will have access to their properties during the work. There may be intermittent traffic delays along Smith Well Road to allow the delivery of material. No water shutoffs are planned for next week.
The project is connected to the elevated water tank under construction, which will provide additional reliability and redundancy to the city’s water system.