Week of Aug. 14, 2023

Haga clic aquí para ver esta informacíon en español.

Update: MacArthur Boulevard Off-Ramp

Closures for Shoring Removal

Contractors are expected to remove temporary shoring at the retaining wall along the northbound MacArthur Boulevard off-ramp. The northbound MacArthur off-ramp is expected to be closed weeknights from 9 p.m. to 5 a.m., during the weeks of Aug. 14 and Aug. 28.  

Demolition of Edinger Avenue Bridge

Barrier Complete

Contractors have demolished the barriers on both sides of the SR-55 bridge over Edinger Avenue one week ahead of schedule. We appreciate the public’s patience to allow contractors to complete the work.

Construction Activities

Lane Channel

Crews are reconstructing the Lane Channel along southbound SR-55, and will continue daytime structural backfill and nighttime shoring removal through the end of August.


Wall Construction Along Cowan

Contractors are constructing two retaining walls along northbound SR-55 along Cowan between Fitch and MacArthur Boulevard. Contractors will continue striping, forming and pouring concrete through August.

In the Community

Thank you to everyone who stopped by the SR-55 Improvement Project booth at this year's City of Santa Ana National Night Out event!


On Friday, Oct. 6, the SR-55 Public Outreach team will be hosting a Project booth at the 66th Annual Tustin Tiller Days Festival. Stop by to learn about construction activities and sign-up for project updates! We look forward to seeing you there!

Closures and Detours Map

Bookmark the closures and detours map for quick access to real-time construction information. Click on the construction icons to view activities and closures.

Business Spotlight: Green Planet Hauling

This week's Focus on 55 business spotlight is Green Planet Hauling, a licensed garbage collection company dedicated to preserving the environment. They remove residential, commercial, and bulky items with ease. Same day services are available!


1324 South Van Ness Ave., Santa Ana, CA 92707

888-899-9368

greenplantet22@gmail.com

https://greenplanethauling.com


To learn more about OCTA's Focus on 55 Program, including official rules and eligibility, visit octa.net/Focuson55 or click here to enroll your business today.

About the Project

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction. Also, the project will add merge lanes between several interchanges and stripe carpool lanes for continuous access, augmenting safety on the freeway by making merging easier. These enhancements are expected to create a better, smoother driving experience for motorists.