Week of April 10, 2023
Construction activity continues along the I-10 throughout the project area.
- Initial bridge widening activities have started at several locations throughout the project, and will continue for the next several months.
- Earthwork, pile driving, irrigation, and minor demolition work will continue along eastbound and westbound I-10.
- Brush clearance and temporary fence installation throughout the project is complete.
Upcoming Closures
Due to heavy downpours from recent storms, crews will be repairing potholes and drainage systems along eastbound and westbound I-10 throughout the project.
Monday, April 10 - Thursday, April 13, 7 p.m. - 5 a.m.
- Intermittent single-lane and shoulder closures along eastbound and westbound I-10
Wednesday, April 12 & Thursday, April 13, 7 a.m. - 3 p.m.
- Single-lane closures along eastbound and westbound I-10
Please note, construction is dependent on many variables including weather, construction material, and crew availability. All schedule information is subject to change.