495 NEXT Project

Lane Closures and Traffic Changes

March 6 - March 12, 2023

The following construction-related lane closures and traffic changes are planned to occur in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers should expect potential delays when traveling in this area, and are encouraged to visit 511virginia.org for current information on travel conditions and work zones in Virginia. All construction-related work and closures are subject to change based on weather and other factors.

Upcoming Highlights

  • Daytime single lane closures on I-495 North.
  • Nighttime multi-lane closures on I-495 North and South, including triple left lane closures on I-495 South throughout the project corridor.
  • Daytime mobile lane closures on I-495 North and South.
  • Daytime turn lane closures and ramps narrowing on the Georgetown Pike/I-495 South and North interchange ramps.
  • Daytime and mobile closures on the Dulles Toll Road and Dulles Access Road just west of I-495.
  • Daytime flagging operations on Lewinsville Road.

Lane Closures 

I-495 (CAPITAL BELTWAY)


I-495 North and South


Monday, March 6, through Thursday, March 9, 9:30 a.m. to 3 p.m.

Single left lane closures on northbound and southbound I-495 between the George Washington Memorial Parkway and Old Dominion Drive to support bridge work, jack and bore work, and/or median sign structure work.


Monday, March 6, through Saturday, March 11, 9:30 p.m. to 5 a.m.

Triple left lane closures on southbound I-495 throughout the project corridor for joint repairs. Note: this work is scheduled to take place nightly for the next two months.


Monday, March 6, through Friday, March 10, 9:30 p.m. to 5 a.m.

Double right lane closures on northbound I-495 from Lewinsville Road to Georgetown Pike for sound wall demolition and saw cutting for joint repairs.


Monday, March 6, through Friday, March 10, 9:30 a.m. to 3 p.m.

Mobile alternating (left/right) single lane closures on northbound and southbound I-495 throughout the project corridor for traffic maintenance and roadway repairs.


I-495 /Georgetown Pike Interchange


Monday, March 6, through Friday, March 10, 9:30 a.m. to 3 p.m.

The Georgetown Pike westbound left turn lane will be closed and the ramp to southbound I-495 will be narrowed to support saw cutting and excavation work to widen the ramp.


Monday, March 6, through Friday, March 10, 9:30 a.m. to 3 p.m.

The eastbound Georgetown Pike left turn lane to northbound I-495 will be closed to support bridge abutment work.


Monday, March 6, through Friday, March 10, 10 p.m. to 5 a.m.

The westbound Georgetown Pike ramp to southbound I-495 will be narrowed and the Georgetown Pike through lane will be narrowed (no lane closures) to support grading and asphalt work to prepare for a lane shift.


DULLES CORRIDOR INTERCHANGE 


Monday, March 6, through Thursday, March 9, 9:30 a.m. to 3 p.m.

Single left lane closure on the westbound Dulles Toll Road between Rt. 123 and I-495 to support embankment placement and drainage work.


Monday, March 6, through Thursday, March 9, 9:30 a.m. to 3 p.m.

Alternating (left/right) single lane closures on the eastbound Dulles Access Road between I-495 and Rt. 123 to support bridge work.


Monday, March 6, through Friday, March 10, 9:30 a.m. to 3 p.m.

Mobile single lane closure on the eastbound and westbound Dulles Toll Road between Rt. 123 and I-495 for traffic maintenance work.


LEWINSVILLE ROAD


Monday, March 6, through Friday, March 10, 9:30 a.m. to 3 p.m.

Flagging operations to alternate single traffic lanes will be in effect on Lewinsville Road for bridge demo work.

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange. Learn more about the traffic change here.

See the new traffic pattern here.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project. Learn more about the traffic change here.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scotts Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

mainphoto1722.png

Learn More About the Project


Check out www.495NEXT.org for additional information.


Sign up here to receive project email updates.



laptop_495EX website.png

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Brent McKenzie, 571-326-5609

Lane Construction, John Undeland, 703-785-3461