Construction Update

December 18, 2024

Upcoming Activities

On Thursday, December 19 starting at 10:00 p.m., the old traffic signals on the north side of 9000 South at 1510 West will be removed and the new traffic signals will be installed. Police officers will be directing traffic during removal and installation.


Through 5:00 a.m., drivers can expect several temporary closures at the intersection lasting up to 30 minutes each while the old poles are removed and the new poles are installed. Plan of delays and consider using an alternate route.

Holiday Break

Crews will take a holiday break starting December 21 and returning January 2. Two lanes will remain open in both directions and the speed limit will remain 35 miles per hour.


Have a happy holiday season and Happy New Year.

Traffic and Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo
UTA Logo

UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments.

Visit UTA's website for specific stop information.

Safety

Pedestrians and bicycles are not allowed on 9000 South over the Jordan River. Please see the approved detour route for pedestrians and bicycles.

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #5626

Email - widen9000south@utah.gov

Project Website - www.udotinput.utah.gov/widen9000south