Monthly Newsletter

Charlotte Street Webpage

3 Week Charlotte Street Outlook

Week of April 10


Working: Estes to Greeley


Construction will continue on Charlotte from Estes to Greeley. They will install the water main in this segment of the roadway. Xcel will be relocating 3 light poles in the ROW. Parking will be prohibited on Charlotte along these two blocks during this time frame.


2 trees will be removed between Freemont and Greeley on the northside (in front of 711 Charlotte Street). Here is a copy of the reports from the arborist.

 

Gas installation will continue from Estes to Columbine during this time. It is anticipated the gas company will complete their scope of work before departing the site completely.


Week of April 17

Working: Estes to Greeley


Construction will continue on Charlotte from Estes to Greeley. The contractor intends to complete the water main this week. At the same time they will begin connecting water services to the homes and residents will be notified 48 hours prior to the service being connected. Parking will be prohibited on Charlotte along these two blocks during this time frame.


Week of April 24

Working: Estes to Greeley


Construction will continue on Charlotte from Estes to Greeley. Connection of water services to the homes and residents should be completed this week. Affected property owners will be notified 48 hours prior to the service being connected.


Following completion of the water services, the contractor will install reinforced concrete pipe (RCP) for the Storm Drain and complete the storm drain in this section between Estes and Greeley. Installation of curb and gutter will also be completed. Parking will be prohibited on Charlotte along these two blocks during this time frame.


During construction in this segment, the contractor will be moving trash cans to a location for the solid waste trucks to pick up all of the trash and recycling for the residents and then moving the cans back to their home locations. Access is accommodated through the alleyways behind the homes. 


Crews will be working on Saturdays from 8 am - 4 pm to help with catch up from the snow days and delays that have occurred.

Visit johnstownco.gov/CharlotteSt2023 for more information
Facebook  Twitter  Instagram

You are receiving this email because you subscribed to the Town of Johnstown's News Updates email list. If you'd like to stop receiving emails on this topic, you can manage your preferences using the Unsubscribe link below. Thanks for staying engaged with your Town!