Week of April 10
Working: Estes to Greeley
Construction will continue on Charlotte from Estes to Greeley. They will install the water main in this segment of the roadway. Xcel will be relocating 3 light poles in the ROW. Parking will be prohibited on Charlotte along these two blocks during this time frame.
2 trees will be removed between Freemont and Greeley on the northside (in front of 711 Charlotte Street). Here is a copy of the reports from the arborist.
Gas installation will continue from Estes to Columbine during this time. It is anticipated the gas company will complete their scope of work before departing the site completely.
|