Temporary daytime road closure
Space Center Drive at Platte Avenue
October 5 - 8

Construction is in progress to replace the eastbound and westbound bridges on Platte Avenue over Sand Creek between Wooten Road and the Powers Boulevard Interchange to improve safety.

Median removal and paving
The Platte Avenue over Sand Creek project will utilize a temporary road closure October 5 - 8 at Space Center Drive, weather and resource dependent. Traffic will be detoured at the south end of Space Center Drive each day from 9 a.m. - 3 p.m. Access to Space Center Drive at the north end (Galley Road) will remain open.


Traffic Impacts October 5 - 8

  • Space Center Drive at Platte Avenue, will implement a full road closure at the south end of Space Center Drive Tuesday through Friday, October 5 - 8, each day from 9 a.m. - 3 p.m., for the removal of median and paving. Access to the north end of Space Center Drive (Galley Road) will remain open.

  • Detour - Traffic (including bicyclists and pedestrians) on Platte Avenue will be detoured at Wooten Road north to Galley Road and east to the Powers Interchange, Tuesday through Friday, October 5 - 8, each day from 9 a.m. - 3 p.m. Alternate access to the area also will be available at Babcock Road.
All business access will remain open throughout construction. Motorists are advised to take alternate routes when possible.
PSC Phase 2 demo
Ongoing Traffic Impacts
  • Traffic control measures are in place. Please use caution
  • Construction activity is behind barrier along the median area of bridges
  • Speeds reduced to 35 mph in the work zone
  • Bicyclists and pedestrians are reminded to seek alternate routes during construction
Background
The bridges are approaching the end of their service life (built in 1956), suffering from prior flood damage (2008) and overall degradation of the structures. The project will replace the two separate bridges with one bridge structure. The project will also add sidewalks along the north and south sides of Platte Avenue over the creek to accommodate the future Sand Creek Regional Trail under the Platte Avenue bridge.
Stay in touch
Find more information about this project: ColoradoSprings.gov/PSCBridge
Project Hotline: 719-634-5056

To receive project progress enewsletters, send an email to: PlatteSandCreekBridges@gmail.com requesting to be added to notification list.

Note: If you unsubscribe from this enewsletter, you will unsubscribe
from ALL Bachman pr project enewsletters. If you wish to no longer
receive this specific project enewsletter but want to continue receiving
other project communications that you previously expressed interest in,
please hit “reply” to this email and key in the message "REMOVE." Thank you.

Project Team
  • City of Colorado Springs Project Manager - Kevin Diekelman and Senior Engineer - Aaron Egbert
  • Engineering Consultant - Wilson & Co. Engineering
  • Construction - Lawrence Construction
  • Public Information - Bachman pr