SHARE:  

MONDAY, JUNE 17, 2024


Two-week project outlook



Monday, June 17 and Tuesday, June 18

  • Drainage installation on Fifth Street (Fourth to Grove).
  • Parking restrictions: No parking on Fifth Street between Fourth and Grove streets during work hours.


Wednesday, June 19

  • Drainage installation on Fifth Street (Fourth to Grove)/ Grove Street (Fourth to Fifth).
  • Parking restrictions: No parking on Fifth Street between Fourth and Grove streets or Grove Street between Fourth and Fifth streets during work hours.


Thursday, June 20 through Friday, June 21

  • Drainage installation on Grove Street (Fourth to Fifth).
  • Parking restrictions: No parking on Grove Street between Fourth and Fifth streets during work hours.


Monday, June 24

  • Drainage installation on Grove Street (Fourth to Fifth)/Fifth Street (Grove to Chestnut).
  • Parking restrictions: No parking on Grove Street between Fourth and Fifth streets, or on Fifth Street from Grove to Chestnut streets during work hours.


Tuesday, June 25 through Friday, June 28

  • Drainage installation on Fifth Street (Grove to Chestnut).
  • Parking restrictions: No parking on Fifth Street from Grove to Chestnut streets during work hours.


Please note, the above schedule is subject to change due to weather and other conditions.


Unitil installing gas main on Grove Street


Unitil contractors will begin installing a new gas main on Grove Street between Fifth and Sixth streets starting this week, with work estimated to continue through Friday, July 12. The contractors will have flaggers to help manage traffic. The work is separate from the city's reconstruction project.


Please return 'Permission to Enter' forms


The city still needs Permission to Enter forms from a few property owners. Permission to Enter temporarily allows the contractor to be on private property to perform project work, such as constructing sidewalks.


Please return the forms to the City of Dover as soon as possible. Questions? Contact Assistant City Engineer Jillian Semprini at j.semprini@dover.nh.gov or 603-516-6450.



More information


Find more information about the project at the dedicated project webpage https://www.dover.nh.gov/government/city-operations/community-services/projects/fifth-street-grove-street-reconstruction-project/ or call Community Services at 603-516-6450.


Forwarded this email? To sign up, visit https://bit.ly/dovernewsletters, and add “Project updates: Fifth Street and Grove Street Reconstruction Project” to your current email subscription list.