Driveway and sidewalk work is now complete on the east side of Center Point Road from Coe Road to the north driveway at Aggie O’Shear’s. Southbound traffic has been shifted to the new pavement at the railroad tracks which has allowed removal of the pavement on the west side between Coe Road and Lake Avenue. The pavement has been removed in stages to maintain at least one driveway to access the businesses on that west side at all times.
Over the next two weeks, expect to see the completion of all of the utility work as well as the start of paving on the east side from Aggie O’Shear’s to Lincoln Avenue and the west side from Coe Road to F Avenue.
Please reach out to a member of our team if you have any questions.
|