HART Executive Director and CEO Lori Kahikina, P.E., along with Deputy Executive Director Rick Keene, joined the Rick Hamada show alongside Vance Tsuda, Project Director for the Honolulu Rail Transit Project. During the discussion on May 3, 2024, the executives highlighted the strength of transparent leadership and teamwork within the agency, in addition to the efforts in preparing for substantial completion and the anticipated opening of Segment 2 of the Project.
Project Updates at a Glance:
-
SEGMENT 2 - Airport Guideway and Stations: Core Systems installation is ongoing; track energization on the guideway and testing is anticipated to begin in the next few months.
-
SEGMENT 3 - City Center Guideway and Stations (CCGS): Utility relocation work is ongoing in Downtown/Iwilei and Kakaako. CCGS Design-Build Contract Procurement is ongoing, with bid/proposals due in July 2024.
‘The HART Hour,’ airs every other Friday from 7 am to 8 am and invites listeners to call in with questions.
Previous episodes can be accessed on the iHeart podcast page:
|