Work continues to progress on the Oakland Road project at multiple locations.
 
Houston Street
·    Curb and gutter work and driveway replacements are complete
·    Tops of the storm sewer intakes are being installed now
·    If temperatures fall and rain is forecasted in the upcoming weeks, sod will be placed. If not, sod will be placed after August 15.
 
Miami Court
·    Driveway replacements are complete
·    Tops of the storm sewer intakes are being installed now
·    If temperatures fall and rain is forecasted in the upcoming week, sod will be placed. If not, sod will be placed after August 15.

Oakland Road
·    Permanent pavement markings have been installed from Center Street to Miami Court
·    Water main installation is complete between Miami Court and Golf Street and along Golf Street from Oakland Road to 42nd Street
·    Storm sewer work will begin next week between Miami Court and Golf Street
 
Traffic Impacts
·    Oakland Road is closed to through traffic between Miami Court and Golf Street; residents have access
·    Northbound through traffic is encouraged to detour from Oakland Road over to Center Point Road via 32nd Street at the south end
·    Southbound through traffic is currently detoured at Golf Street to 42nd Street and then to Center Point Road at the north end

If you have any questions, please do not hesitate to contact a member of our team.