WEEKLY UPDATE: April 17 - April 23, 2021
COVID-19 UPDATE
Work continues on essential projects to support critical housing and infrastructure for the campus community. This work continues to be done with close attention to the health and safety of construction workers. All planned work is subject to change based on shelter in place orders.

For more information, please see the Stanford Health Alerts website.
WEST CAMPUS
HERRIN DEMOLITION:
  • Please use caution and follow the direction of construction signage and flaggers at Lomita and Roth.
  • Structural demolition of the Herrin buildings is now complete. Work will continue to remove demolition debris from the site.

GATES COMPUTER SCIENCE RENOVATION:
  • Demolition of interiors underway.
  • One lane on Jane Stanford Way is impacted due to debris boxes in front of the building.
  • Please be aware of additional truck traffic on Jane Stanford Way, Via Palou, and Via Ortega.

CAMPUS DRIVE:
  • Domestic water underground utility replacement work through 4/24. Work hours from 8:30am to 4:30pm. 
  • Traffic will be impacted on Campus Drive with lane adjustments and flaggers. 
  • Expect delays on Campus Drive between Junipero Serra Blvd and Santa Teresa. 

HISTORY CORNER:
  • Utilities replacement project continues through Summer 2021.
  • Work will be done at nights, Mondays through Thursdays from 6pm to 4:30am.
  • History Corner Access Limitations:
  • Buildings 1 & 10: The doors on the north side that lead into the History Corner will be blocked. Occupants will be directed to use the south entrances towards the Church.
  • Buildings 20 & 40: No doors will be blocked; however, access to nearby walkways into the History Corner will be closed. 
  • Buildings 120, 160, 170 & 200: The doors on the south side that lead into the History Corner will not be blocked, but occupants will be directed toward doors that lead to Jane Stanford Way, Lasuen Mall, or Memorial Court. The lower and upper exits into History Corner on the south side should only be used in emergencies.
EAST CAMPUS
GRADUATE SCHOOL OF EDUCATION:
  • Underground utility relocation and site work for the GSE building continues; work hours are 7am to 5pm, Monday through Friday.  
  • Available here is a map of the area under construction, area used for laydown, and the alternate bike and pedestrian paths.  
  • This is phase 1 of many that will be occurring around the GSE Building and Barnum to prep for an upcoming construction project. 

JANE STANFORD WAY & MANZANITA TURN-AROUND:
  • Expect one-way traffic on Jane Stanford Way along Manzanita Garage through 4/16.
  • Please follow the direction of all construction signage and traffic control personnel. 
  • This work may be noisy at times.

ESCONDIDO VILLAGE GRADUATE RESIDENCES:
  • Area drains will be installed in the bike parking area between Bldg A and Studio 2 to mitigate ponding during rainy weather.
  • Work duration: 4/21 to 4/27. There will be no weekend work.

ARRILLAGA HALL UNDERGROUND INVESTIGATION:
  • The path between Arrillaga Hall and Ford Center continues to be impacted through the end of the month to evaluate the underground soil mitigation.
  • Use caution while traveling in the area.

GREEN LIBRARY EAST - HOHBACH HALL:
  • Hohbach Hall Green Library East 1st floor TI project.
  • Work hours are from 5:00am to 2:30pm.
  • Interior demolition.
  • MEP overhead rough ins.
  • Wall layout markings underway.

CABRILLO-DOLORES FACULTY HOMES:
  • On 4/22 & 4/23, PG&E will complete the gas connections at multiple locations around the project site. 
  • Once the connections are complete the contractor will backfill the holes. 
  • Expect heavy equipment in the area, including trucks and excavation equipment. 

CONSTRUCTION MAP
Click to view interactive construction map.
SAFETY REMINDERS
  • Avoid using cell phones while walking or biking, especially around construction sites.
  • Pay attention to your surroundings as you walk, run, bike, or drive around campus.
  • Anticipate detours in construction areas and follow the directions of flaggers and signs.
  • If you're riding a bike, follow the rules of the road - stop at signs.
  • Allow a little more time than usual to travel on campus. 
ABOUT US
HEADS UP is a campaign designed to inform the campus community of construction activity and to provide strategies for navigating safely, whether on foot or on wheels.

Look out for HEADS UP signs around campus to warn you of construction-related detours or new circulation behaviors.

You are receiving this email as a valued member of our campus community.
Thank you in advance for your understanding and cooperation.
Please feel free to forward this email or encourage others to subscribe.
Questions or feedback? Reach us at headsup-updates@lists.stanford.edu

To report disability access concerns related to any construction occurring on campus, 
including disabled parking or path of travel issues, please contact disability.access@stanford.edu