495logo.jpg

495 NEXT Project

Lane Closures and Traffic Changes

November 11 - November 17, 2023

The following construction-related lane closures and traffic changes are planned to occur in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers should expect potential delays when traveling in this area and should visit 511virginia.org for real-time information on work zones and lane closures. All work is subject to change based on weather and other factors.

495 NEXT Project Area Map

Upcoming Highlights

  • THIS WEEKEND: There will be no Project-related lane closures over the Veteran’s Day holiday weekend


  • I-495 North and South – Day and nighttime single lane closures


  • I-495 South – Nighttime double lane closures


  • I-495 South to Georgetown Pike exit – Daytime single lane closures


  • Westbound Georgetown Pike bridge over I-495 – Daytime single lane closures


  • Live Oak Drive and Balls Hill Road – Daytime flagging operations


  • Westbound Dulles Toll Road – Daytime single lane closures


  • Eastbound Dulles Toll Road/Airport Access Road to I-495 North Ramp – Nightly ramp closure with detour in place

Lane Closures 

I-495 (CAPITAL BELTWAY)


I-495 North


Monday, November 13, through Thursday, November 16, 10 a.m. to 3 p.m.

Single right lane closure on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for drainage, sound wall, embankment, and excavation work.


Monday, November 13, through Friday, November 17, 10 a.m. to 3 p.m. and 9:30 p.m. to 5 a.m.

Alternating single mobile lane closures on northbound I-495 throughout the project corridor as needed for maintenance work and traffic management.


Monday, November 13, through Friday, November 17, 9:30 p.m. to 5 a.m.

Single right lane closure on northbound I-495 between Lewinsville Road and the George Washington Memorial Parkway for the removal of drainage structures.


I-495 South


Monday, November 13, through Thursday, November 16, 9:30 a.m. to 2:30 p.m.

Single right lane closure on southbound I-495 between Georgetown Pike and Dulles Toll Road for drainage, excavation, embankment, and sound wall work.


Monday, November 13, Tuesday, through Thursday, November 16, 9:30 p.m. to 5 a.m.

Double right lane closures on southbound I-495 at the Scott's Run bridge for demolition work and overhead sign removal.


Monday, November 13, through Friday, November 17, 9:30 a.m. to 2:30 p.m. and 9:30 p.m. to 5 a.m.

Alternating single mobile lane closures on southbound I-495 throughout the project corridor as needed for maintenance work and traffic management.


Monday, November 13, through Friday, November 17, 9:30 a.m. to 2:30 p.m.

Single left lane closure on the ramp from southbound I-495 to Georgetown Pike for pile driving and excavation work.

LIVE OAK DRIVE


Monday, November 13, through Friday, November 17, 9:30 a.m. to 3 p.m.

Live Oak Drive will be reduced to a single lane near the swim club and bridge for waterline work. Flagging operations alternating single traffic lanes will be in effect.

BALLS HILL ROAD


Monday, November 13, through Friday, November 17, 9:30 a.m. to 3 p.m.

Balls Hill Road will be reduced to a single lane at the Live Oak Drive intersection for bridge support work. Flagging operations alternating single traffic lanes will be in effect.

GEORGETOWN PIKE INTERCHANGE


Monday, November 13, through Friday, November 17, 9:30 a.m. to 3 p.m.

Single right lane closure on westbound Georgetown Pike on the bridge over I-495 for pile driving and bridge abutment work.

DULLES CORRIDOR INTERCHANGE 


Monday, November 13, through Thursday, November 16, 7 p.m. to 5 a.m

The ramp from the eastbound Dulles Toll Road/Airport Access Road (Route 267) to northbound I-495 will be closed during overnight hours for beam setting. Motorists should follow the posted detour. Learn more about the work and detour here.


Dulles Toll Road


Monday, November 13, through Thursday, November 16, 9:30 a.m. to 3 p.m.

Single left lane closure on westbound Dulles Toll Road (267 Connector) near the I-495 interchange for drainage, embankment, and bridge work.

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange. Learn more about the traffic change here.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project. Learn more about the traffic change here.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scotts Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

Learn More About the Project


Check out www.495NEXT.org for additional information.


Sign up to receive project email updates.



laptop_495EX website.png

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461