North Coast Highway 101 Leucadia Streetscape Update

December 2023   



City Prepares for Segment C West and Drainage Improvements of Leucadia Streetscape Project  

 

The City of Encinitas appreciates the support and patience from the community during construction for the first segments of the Leucadia Streetscape project. We are proud to see the improvements enjoyed by the community.  

 

Currently, we are preparing for the next segment of the Leucadia Streetscape project from Jupiter Street to La Costa Avenue, which is scheduled to begin construction in January 2024.  

 

The goal of the Leucadia Streetscape project is to preserve and revitalize the North Coast Hwy 101 Corridor, and this upcoming segment includes many important safety, transportation, and sustainability enhancements, as well as improved drainage infrastructure. Please visit the City website to view the project map.  



Next Steps  

 

Blue Pacific Engineering and Construction was awarded the construction contract by the Encinitas City Council on September 13, 2023.  Construction will begin in January 2024 and is expected to be completed in Summer 2025. Leucadia Streetscape project updates can be found on the city website.


If you own a business along North Coast Hwy 101 between La Costa Avenue and Jupiter Street, the City encourages you to take this survey to identify your construction concerns for your business.  

 

Here is a summary of the timeline based on the most current project schedule.  

 

Streetscape Segment C West – Jupiter Street to La Costa Avenue  

  • Winter 2022 – Spring 2023: Project funding secured 
  • Summer 2023 – Winter 2023: Advertise and award construction contract  
  • January 2024: Streetscape construction begins 
  • Summer 2025: Construction Completion 

 

Streetscape Drainage Segment C – Jupiter Street to La Costa Avenue 

  • Summer 2023 – Winter 2023: NEPA process and grant certified by HUD, advertise construction contract and award construction contract 
  • January 2024: Drainage infrastructure construction begins 
  • Summer 2025: Construction Completion 



Project Improvements  


This current segment of construction will provide the following benefits:  

  • Two new traffic roundabouts at Grandview and Jupiter Streets 
  • Parking along North Coast Highway 101, including areas for business deliveries on the west side 
  • New medians, landscaping, trees, and street lighting 
  • Repaving and restriping of traffic lanes 
  • Dedicated bike lane from Jupiter Street to La Costa Avenue 
  • Pedestrian signal at Avocado Street 
  • New and expanded sidewalks  
  • Improved crosswalks with flashing lights 
  • Storm drain infrastructure to address historic flooding 