CONSTRUCTION UPDATE
Since our last update we have had some respite from COVID, although we did not anticipate the significant weather system that developed bringing wet weather to South East Queensland.

Our builder, Broad Construction has made significant progress towards completing the retail east basement car park and have poured their way through the future Dan Murphy's floor slab.
To give you some insight into how the structure is being progressed to Stage 1 works and what has been achieved or will be over the next little while:

  • 7 of the 9 basement slabs have been formed with formwork, reinforced with steel, and poured with concrete. The remaining two sections of the basement slab are to be completed by mid-April 2022.
  • Approximately a third of the ground/level 1 slab has been formed, reinforced, and concreted. This includes the Dan Murphy's slab.
  • Formwork has been erected to the retail arcade. There will be a flurry of work through mid-April 2022 to have this space reinforced and concreted.
  • The slabs to the Dan Murphy's slab and retail specialties such as Crafty's require detailed design coordination to ensure slab penetrations and setdowns for building services and cold rooms are constructed with precision.
  • The eastern ramp to the basement car park has been formed, reinforced, and concreted.
  • Blockwork has been completed to the basement walls (eastern car park only)
  • Precast panelling is being manufactured offsite at Rocklea and transported to site where it will be erected in place.
  • The lift cores (commuter deck and cinema) will continue to rise with the structure following it.
Ferny Grove Central Now Leasing
Immerse yourself within a vibrant, community-centric hub where new business can truly flourish.
 
Retail tenancies available for lease now prior to construction completion.
 
Reach out to Taylor from JLL to enquire about retail opportunities.
Remember to follow us on social media!