Monthly Newsletter

Charlotte Street Webpage

3 Week Charlotte Street Outlook

Week of August 14


Working: Greeley to Jay

Crew are waiting for Xcel Energy to complete gas line services


Working: Estes to Columbine

Crews will continue BacT testing and water line installation

Week of August 21


Working: Greeley to Jay

Crews will starting the removal of existing dirt in the area and begin the installation of curb and gutter

Week of August 28


Working: Greeley to Jay

Crews are expected to start to install aggregate base course and the bottom lift of asphalt this week

During construction in this segment the contractor will be moving trash cans to a location for the solid waste trucks to pick up all of the trash and recycling for the residents and then moving the cans back to their home locations. Access is accommodated through the alleyways behind the homes. 


Crews will be occasionally working occasional Saturdays from 8 am - 4 pm to help with catch up from weather delays that have occurred.

 

Visit johnstownco.gov/CharlotteSt2023 for more information
Facebook  Twitter  Instagram

You are receiving this email because you subscribed to the Town of Johnstown's News Updates email list. If you'd like to stop receiving emails on this topic, you can manage your preferences using the Unsubscribe link below. Thanks for staying engaged with your Town!