Starting as early as 6 a.m. on Monday, Nov. 6, the Hilltop East entrance will be closed until 6 a.m. on Tuesday, Nov. 7, as crews continue paving operations. Motorists attempting to access or exit the shopping center during this time can utilize the alternate entrances along Laskin Road.
As part of the ongoing operations, there will be alternating closures of the entrance to the Linkhorn Bay Condominiums. The easterly entrance to the condominiums will be closed the starting Tuesday, Nov. 7, for grading in preparation for paving operations until for an estimated 24 hours. Beginning as early as Wednesday, Nov. 8, the westerly entrance will be closed for crews to perform grading. The work on the entrance to the Linkhorn Bay Condominiums is expected to continue through Sunday, Nov. 12.
Access to properties throughout this corridor will be maintained at all times.
This work is weather-dependent, and the schedule is subject to change.
|