  • Nighttime single lane closures are scheduled along eastbound I-10 Monday through Thursday, 7 p.m. - 5 a.m., for crews to safely continue bridge demolition and concrete pours


  • Earthwork and grading operations continue throughout the project


  • Drainage installation, bridge widening, approach slab construction, and concrete pours continue throughout the project


  • Hot Mix Asphalt (HMA) placement and concrete paving begins this week and will continue throughout the Fall
Project Updates

Give Us a Follow!

Want the latest project updates and closures information? Follow the project via social media on Facebook and X (formerly Twitter).

Project Background
The I-10 Desert Rehab Project segment is a 13-mile stretch of the I-10 freeway near Coachella in Riverside County, between 1.8 miles east of the Dillon Road Interchange and 2 miles east of the Cactus City Rest Area. Construction will take place over the next 3.5 years and includes repaving I-10, updating lane striping, and the addition of an eastbound truck climbing lane. The Cactus City Rest Area will also be closed for 1-2 months during construction. 

In addition to repairing and restoring existing roadway pavement and adding an eastbound truck climbing lane, the I-10 Desert Rehab Project will install electric vehicle charging stations at the Cactus City Rest Area, replace and upgrade bridge railings, guardrail systems, and roadway signage, and improve roadway infrastructure including drainage and stormwater treatment systems.