Work continues to move along. Pavement and driveways are complete in Stage 1 on the map below. The contractor is placing dirt behind the curb and doing general clean up today.
Starting on Monday, June 28, they will open Stage 1 to traffic and close Stage 2. 66th Avenue will remain closed, but the closure area will shift west to the Stage 2 area.
We encourage business to help notify customers of this traffic shift. Some specific updates include:
- Atlantic Coca-Cola Bottling Company’s western driveway will be closed in Stage 2; access will need to come from the east (the 6th Street SW-side)
- XTRA Lease’s permanent driveway was complete in Stage 1; access will also need to come from the east starting on Monday.
- Custom Hose’s loading dock was complete in Stage 1 and will be open starting on Monday.
- All other access remains unchanged.
Please do not hesitate to reach out to us if you have any questions.