Week of August 21


Working: Greeley to Jay

  • Gas line services have been completed. 
  • Start removal of existing dirt and prep for curb and gutter. 


Working: Estes to Columbine

Bac-T waterline testing has been completed and installation of services will start.

Week of August 28


Working: Greeley to Jay

Crews will...

  • Start the installation of curb and gutter. 
  • Install storm inlets. 
  • Start installing the aggregate base course of the road prior to paving. 

Week of September 4


Working: Greeley to Jay

Crews will...

  • Start work on concrete drive aprons and ADA ramps. 
  • Start installing the bottom lift of asphalt. 

During construction in this segment between Greeley and Idaho the contractor will be moving trash cans to a location for the solid waste trucks to pick up all of the trash and recycling for the residents and then moving the cans back to their home locations. Access is accommodated through the alleyways behind the homes. 


Crews will be working occasional Saturdays from 8 am - 4 pm to help with catch up from weather delays that have occurred.

 