Construction on the Pure Water Oceanside pipeline on Coco Palms will continue during the monitoring well delay. Coco Palms Dr. will continue to be closed for the next few months. Understanding this road is an important pedestrian thoroughfare, the project team is exploring the option of pedestrian access.
Work on the south side of Coco Palms Dr. near the El Camino Real intersection begins this month for pipeline construction. Parking on the south side of Coco Palms Dr. will be closed during this work period and "no parking" signs will be posted.
Monitoring well work in Fireside Park will begin in early February with mostly daytime work with the possibility of some 24/7 construction for critical activities. Sound walls will be installed to reduce noise. Drilling and development is estimated to take six weeks with infrastructure work completed by spring.