Paving was placed today on remaining portions of O Avenue between 18th Street and 20th Street. Over the next 2-3 weeks, side street intersections, driveways and sidewalk will be constructed in this segment as weather allows. If weather continues to cooperate, this area will be graded and sodded. Otherwise, the areas will be rough graded and receive temporary winter cover to reduce erosion.

While this work is underway, new storm sewer will be extended from 20th Street to 24th Street. Work on the box culvert between 24th Street and 30th Street is expected to begin at the end of October and will continue into winter as weather allows, along with installation of water main to 26th Street.

Relocations of private utilities from 24th Street to Edgewood Road continues, including installation of new gas main and utility poles. Relocation of phone and fiber optic lines will begin at a later date.

As always, if you have questions or concerns, you are welcome to contact a member of our project team.