Crews are scheduled to remove the falsework at the Talbert bridge over I-405. This work will require SB and NB full directional freeway closures between Brookhurst Street and Euclid Street.
NB nightly full freeway closures are set to continue 10 p.m. to 5:30 a.m.:
- Tonight, Thursday, Jan. 14
- Monday, Jan. 25 through Friday, Jan. 29*
SB nightly full freeway closures are set for 10 p.m. to 5:30 a.m.:
- Monday, Jan. 18 through Friday, Jan. 22
- Monday, Jan. 25 *
- Tuesday, Jan. 26*
*Only one direction is planned to be closed. If SB work has not been completed, it will be closed. Otherwise, northbound (NB) will be closed.
Sign up for project-wide and bridge-specific construction alerts at
bit.ly/405-signup.