SHARE:  
March 22, 2021
One Year Ago ...

It’s hard to believe that it was one year ago that we last gathered in person for worship and to celebrate the progress of the Sanctuary Preservation and Readiness Project at the beautiful home of Geoff and Alison Rusack. Little did we know what was in store for us all: the sickness and sadness, the loneliness, the thankfulness for our many blessings, the new ways of connecting electronically, the losses experienced for our workers and business owners, and so much more.

As the shut-down took hold and our campus was closed, the project oversight team transitioned from twice-per-week, in-person meetings to one meeting by phone every week. We gathered electronically with our teammates from Armstrong Associates and our architect, Bob Easton, AIA. We certainly missed the fellowship of in-person meetings, but we adapted, just like each of you, to our new reality. We kept our foot on the gas and our eye on the budget, addressing each day the remarkable complexity of rebuilding a 120-year-old structure. The regular e-newsletters kept you apprised of our years-in-the-making effort. Stay tuned for more details about the Project that will be discussed at the upcoming Annual Meeting on April 18.

It was impossible to know, of course, that the pandemic would be the perfect time to have our Sanctuary closed for its renovation. We now hone in on the completion of formal construction and the many tasks required to ready the Sanctuary for not just its unveiling as a seismically strong structure, but as our “re”gathering place to remember all that we’ve endured over the past year and begin building up once again our faith and love of our church family.


The Project Construction Committee
Pete Adams
Sheri Benninghoven
Alyson Eyer-Delevett
Tom Mack
Chip Nichols
George Writer
Our Historic Stained Glass Windows Come Home
Craftsmen from Judson Studios were onsite this past week to install virtually all of our stained glass windows that were carefully crated and moved to their Pasadena studios for refurbishment. The move back into the Sanctuary is a sign that formal construction is nearly at an end! While we do not have a set date that our general contractor, Armstrong Associates, will wrap up work, they are beginning to schedule "punch list" meetings ... a wonderful sign!

March 23, 2021
Accessibility Lift Brings All To The Chancel
One of the most significant aspects of our Sanctuary Preservation and Readiness Project was to address the needs of those who are physically challenged. Whether someone struggles with mobility, hearing challenges or vision impairment, our goal was to ensure that anyone and everyone could participate in the practice of our faith during worship service.

In addition to installing hearing assistive technology and much improved lighting, the "new" Sanctuary will include a "lift" that will provide access to each of three levels around the chancel: main floor level, the communion service level from which the clergy and lay ministers will administer Holy Communion, and the altar level. The new, specially-made lift is located on the south side of the chancel. "We worked very hard with our architect, general contractor and lift manufacturer to not only design a functional lift but also to ensure it blended into our beautiful interior as much as possible," said Chip Nichols, chair of the parish's Project Facilities Committee, which is overseeing construction.

A Few Miscellaneous Scenes
Below are a few scenes from inside the Sanctuary taken during the past week:
Top: the interior of the Memorial Chapel with columbarium niches being installed. Note the beautiful beamed ceiling with up-lighting.
Middle: workers performing various tasks near the pews, stained glass windows ... with our new pendant lamps lighting the way.
Bottom: Our main entry doors getting their final touch ups and coat of paint.