Biscayne Beach Surface Parking Lot Update
December 6, 2021

What's Happening:
The seawall, underground utilities, sidewalks, driveway access and drainage system have been completed. Light poles and security camera poles have been installed, the light shields are pending and will be installed in the coming weeks.
Currently, crews are preparing for paving and landscaping installation throughout the site.

Project Overview and Benefits
Located at 8100 Hawthorne Avenue, this project delivers vital improvements to the Biscayne Beach neighborhood, including the construction of a new surface parking lot with 28 spaces, a new drainage system, landscaping, irrigation system, picket fencing and a precast concrete wall. The project will also incorporate new lighting, conduits for security cameras and resilient infrastructure that features a new raised seawall and pervious pavement.
Timeline
The project is on schedule for completion by March 2022.

Construction work hours are weekdays from 8 a.m. to 6 p.m. for the duration of the project. Please note this schedule may change due to weather or unforeseen circumstances.
What to Expect
  • Moderate levels of construction noise is expected during the day.
  • Construction equipment, machinery and workers will be present in the work zone.

Who to Contact
Dexter Peralta
786.265.7443
To learn more about the city’s innovative initiatives, visit www.MBRisingAbove.com.

To request this material in alternate format, sign language interpreter (five-day notice required), information on access for persons with disabilities, and/or any accommodation to review any document or participate in any city-sponsored proceedings, call 305.604.2489 and select 1 for English or 2 for Spanish, then option 6; TTY users may call via 711 (Florida Relay Service).