Pavement on Oakland Road was completed last week between Center Street and 35th Street. The contractor is now working on replacing side streets and driveways. Construction of retaining walls and sidewalks are scheduled to begin next week. Oakland Road between Center Street and 35th Street is expected to open in approximately two weeks. 
 
Utility work is continuing between 35th Street and Hollywood Boulevard, with paving expected to begin within the next two weeks. This section remains closed. 
 
As always, if you have any questions on the project, please don't hesitate to contact us. Thank you for your continued patience!