Westchester County Airport has a few projects underway and we thank Airport Operations for providing the update and photos.
The Taxiway Juliet Rehabilitation Project (Left Photo) that commenced on June 9 was fully completed on June 17. Over 1,500 tons of Bituminous Asphalt was installed and corrected the many discrepancies with the deteriorated asphalt pavement and ponding issues. This project included new Surface Markings and is a great safety enhancement for all users adjacent to Taxiway Juliet.
Take a look at the new SCULLY Anti-Overfill Protection located at the Fuel Farm (Right Photo). This device will prevent the airport's Mobile Fuel Trucks from being overloaded with fuel and venting into the environment. This system also provides for bonding during fuel loading operations.