Trees that fell along 34th Street SE during the storm on August 10 took down utility poles and power and communications lines in the project area. For the time being, project site cleanup and construction are on hold for safety reasons.  

Once work can resume, crews will continue working on the box culvert so the site can be prepped for new pavement. We still anticipate the bridge replacement will be completed this fall and 34th Street will reopen. We will update you on a more specific timeline as soon as we can. 

As always, if you have questions about the project, please do not hesitate to contact a member of our project team. In the meantime, please be safe.