Center Point Rd from Coe Rd to Lincoln Ave

Construction Update | 10-3-2022

The mainline pavement on the east half of Center Point Road is now complete from Coe Road to the north driveway at Aggie O’Shear’s.


A shallow gas main was discovered along the east side, north of F Avenue, which has postponed paving the driveways. MidAmerican Energy Company is scheduled to lower the gas main early this week so that driveway and sidewalk work can continue.


Traffic Pattern Shift This Week:

Southbound traffic will be shifted to the new pavement near F Avenue to allow removal of the pavement on the west side between Coe Road and F Avenue. The pavement will be removed in stages to maintain at least one driveway to access the businesses on that west side at all times.


Thank you for your continued patience.

CONTRACTOR
BWC Excavating
Brandon Hansen
563-321-8669
CITY CONSTRUCTION MANAGER
Eric Bahl
319-286-5531

CITY PROJECT MANAGER
Jennifer Selby
319-286-5622
About the Project
The project on Center Point Road NE stretches from Coe Road to Lincoln Avenue. Improvements include pavement reconstruction, sidewalk replacement, ADA sidewalk ramps, on-street bike lanes, utilities (water main, storm sewer, sanitary sewer), and conversion of the roadway from one-way to two-way traffic. It is scheduled for completion this fall. This is Phase 1 of a two-phase project. Phase 2 includes Lincoln Avenue to J Avenue and will bid in fall 2022 for construction in spring 2023.

Watch a video overview HERE