Work is progressing in Stage 2. All of the underground utility work is complete and weather permitting, the pavement will be poured tomorrow, July 14. The pavement will need a few days to set up and then the driveways will be replaced next week, including:

  • Atlantic Coca-Cola Bottling Company's western driveway
  • ATC’s eastern driveway
  • A driveway at the new gate at 900 66th Avenue

After driveways are set up, Stage 2 will be open to traffic and the project will move west to Stage 3.

As with previous switches, 66th Avenue will remain closed, but the closure area will shift. We will send an additional update as we get closer to switching from Stage 2 to Stage 3, so businesses can notify their customers of the traffic change and access routes. The contractor will also go door-to-door to let businesses know about the change. 

Thank you for your patience. If you have any questions, please reach out to a member of our team.