All of the watermain along Center Point Road from F Avenue to the railroad tracks has been disinfected and passed all testing. The area has been prepared for paving, which is expected to occur early next week. The mainline pavement will be constructed first with driveways and sidewalks to follow. Work will continue to the north in the east half of the roadway as water main passing results come in.
As a reminder, as paving occurs, BWC will notify property owners of driveway impacts. At least one access to all businesses will remain open at all times.
Current Traffic Impacts:
- Center Point Road continues to be reduced to one lane, southbound, with the work occurring in the left lane
- F Avenue is closed at Center Point Road on the east side
Thank you for your continued patience.
|