Center Point Rd from Coe Rd to Lincoln Ave

Construction Update | 9-16-2022

All of the watermain along Center Point Road from F Avenue to the railroad tracks has been disinfected and passed all testing. The area has been prepared for paving, which is expected to occur early next week. The mainline pavement will be constructed first with driveways and sidewalks to follow. Work will continue to the north in the east half of the roadway as water main passing results come in.

 

As a reminder, as paving occurs, BWC will notify property owners of driveway impacts. At least one access to all businesses will remain open at all times.

 

Current Traffic Impacts:

  • Center Point Road continues to be reduced to one lane, southbound, with the work occurring in the left lane
  • F Avenue is closed at Center Point Road on the east side

 

Thank you for your continued patience.

CONTRACTOR
BWC Excavating
Brandon Hansen
563-321-8669
CITY CONSTRUCTION MANAGER
Eric Bahl
319-286-5531

CITY PROJECT MANAGER
Jennifer Selby
319-286-5622
About the Project
The project on Center Point Road NE stretches from Coe Road to Lincoln Avenue. Improvements include pavement reconstruction, sidewalk replacement, ADA sidewalk ramps, on-street bike lanes, utilities (water main, storm sewer, sanitary sewer), and conversion of the roadway from one-way to two-way traffic. It is scheduled for completion this fall. This is Phase 1 of a two-phase project. Phase 2 includes Lincoln Avenue to J Avenue and will bid in fall 2022 for construction in spring 2023.

Watch a video overview HERE