In July, crews continued construction activities along the corridor:
Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue
- Completed drilling for noise barrier foundations along westbound Route 7 between Riva Ridge Drive and Great Passage Boulevard.
- Completed noise barrier post installation along westbound Route 7 between Amanda Drive and Riva Ridge Drive, and started post installation between Riva Ridge Drive and Baron Cameron Avenue.
- Completed noise barrier panel installation along eastbound Route 7 between Reston Avenue and Reston Parkway.
-
Placed curb stone and base asphalt for Stage 3B between Amanda Drive and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
- Began noise barrier post installation along eastbound Route 7 between Baron Cameron Avenue and Delta Glen Court.
-
Continued fine grading for Stage 3A along westbound Route 7 between Colvin Forest Drive and Baron Cameron Avenue.
Area 2: Baron Cameron Intersection
-
Placed cement-treated aggregate and asphalt for Stage 2C and continued intersection reconstruction work.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)
-
Completed stone and asphalt placement for Stage 2 between the pedestrian underpass at Colvin Run Mill Park and Serenity Woods Lane.
- Finished construction of the approach slabs and outer bridge rail, completed deck grooving, and shifted eastbound Route 7 traffic to the new Difficult Run bridge.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Completed drilling for noise barrier foundations along eastbound Route 7 between Atwood Road and Towlston Road, and between Laurel Hill Road and Jarrett Valley Drive.
- Continued storm sewer installation between Newcombs Farm Road and Beulah Road, and between Wolftrap Run Road and Lewinsville Road.
-
Placed curb stone, installed curb, and placed asphalt for Stage 3A between Serenity Woods Lane and Middleton Ridge Road.
- Completed storm sewer installation along the future right turn-lane from westbound Route 7 to the relocated portion of Lewinsville Road.
-
Continued road construction activities at Lewinsville Road in preparation for the upcoming opening of the displaced left-turn lane.
|