Substantial construction in Lexington Center is anticipated to begin on Tuesday, July 6.
The Center Streetscape Project is anticipated to take two construction seasons to complete.
We greatly appreciate the community's patience as we make a safer, brighter, and more accessible Lexington Center. It's important to remember that businesses in the Center will be open during construction!
You can learn more about the project, and sign up for regular email updates, by visiting our website.
Below are the details we sent out in the first Center Streetscape email update:
Construction Activity Week of July 5-9
Crews will begin installing underground drainage structures and pipes within the roadway, mostly toward the curb lines.
Crews will be working in the area of Depot Square for some of the days during the week of July 5-9 - please follow signage to access businesses and Lexpress bus service
Anticipated Traffic & Parking Impacts
Moderate traffic impacts are expected with crews working in the roadway.
Some on-street parking will be impacted in the areas where crews are installing drainage.