Project Update
UTILITIES WORK UPDATE: The gas work for this project is now complete. The westbound lane at Airport Road is no longer closed.
Construction of the remaining sanitary sewer progressing east within Airport Road to about Lakewood Circle is expected to be completed this spring. Springs Utilities will also relocate 20” and 4” gas lines to just north of the bridge prior to the bridge replacement project taking place this fall. Waterlines will be relocated under the bridge during the bridge reconstruction.
Sanitary Sewer Work Schedule:
- Final Sewer Construction: April – May 2021, 4- to 6-week road closure.
Pedestrian access will be maintained throughout the duration of construction.
Replacement of the bridge over Spring Creek requires relocation of water, sewer and gas lines that cross under it. About 2,500 feet of the existing sanitary sewer line is being replaced with a larger pipe to accommodate current needs and future growth in the city. Prior to the start of the bridge replacement work this fall, Colorado Springs Utilities has been installing this 42” sanitary sewer line starting within Valley Hi Golf Course, progressing northeast along the western edge of the course up to the Spring Creek Bridge area.
On-going lane closure: Through approximately May 2021, one lane of eastbound Airport Road will be closed between just east of Chelton and Audubon roads to accommodate construction access to the work area for the new sanitary sewer work on Valley Hi Golf Course. Speed limits reduced to 25 mph through this construction area.
BRIDGE/CULVERT REPLACEMENT PROJECT: The City of Colorado Springs project to rebuild the Airport Road over Spring Creek Bridge this fall will increase its width to accommodate sidewalks and deepen the channel to enable flood flows to pass below the roadway.
Construction will take place during the fall to avoid the risk of Spring Creek channel flooding and washout typically associated with summer monsoon rains.
Temporary improvements made at Airport Road and Marjorie Lee Drive will enable normal traffic operations throughout the summer months prior to the bridge work starting.
Bridge Project Work Schedule:
- Contractor selection: Early 2021
- Bridge Construction project: fall 2021 – spring 2022
Pedestrian access will be maintained throughout the duration of construction.