WHAT:
Crews will demolish the concrete barrier along both sides of the SR-55 bridge over Dyer Road to accommodate the freeway improvements. This work will require these closures:
- Dyer Road under the freeway
- Northbound Dyer Road loop on-ramp
- Two outside lanes in both directions of the freeway at Dyer Road
WHEN:
9 p.m. to 5 a.m. nightly, beginning as soon as Monday, Dec. 16, and continuing for approximately three weeks.
To prepare for demolition, crews will perform nighttime sawcutting activities at the Dyer Road bridge the week of Dec. 9. This work will require directional closures of Dyer under the freeway. Eastbound and westbound Dyer will not be closed simultaneously.
This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
|