SHARE:  

Construction Update

Champlain Parkway Project

DATE: Friday, January 6, 2023

TRAFFIC IMPACTS:

Please note, all work will be restricted to the hours of 7:00 a.m. and 7:00 p.m. Flaggers will be present to assist motorists through the work zone. All roadway and lane closures will reopen during the evening hours and on weekends unless otherwise noted. Access to residential and business driveways will be maintained throughout the work unless alerted otherwise. Businesses will remain open!


Ferguson Avenue is closed at its intersection with Briggs Street and will remain closed 24 hours a day through midweek the week of January 9 to facilitate utility work. After Ferguson Avenue is reopened midweek, Lyman Avenue will close at its intersection with Briggs Street and will remain closed 24 hours a day into the week of January 16 to facilitate utility work. Ferguson Avenue and Lyman Avenue will remain closed over the weekends of January 6 and January 13, respectively.


Morse Place is closed at its intersection with Briggs Street and will continue to be closed early next week to facilitate utility work. The closure will remain in place during active construction hours only, reopening each night and throughout the weekend. During the closure, access to Briggs Street will be maintained via a temporary roadway.



Sears Lane will continue to be closed to thru traffic west of Kaigle’s Service Center. Emergency vehicle access will remain. The pedestrian crossing between Sears Lane and Harrison Avenue will remain open. Vehicle access to the HULA Lakeside Offsite Parking Lot (HULA parking lot) will now be from Lakeside Avenue only.  

CONSTRUCTION ACTIVITIES:

Crews will continue work on utilities next week with a focus on the relocation of water lines and the installation of stormwater infrastructure, duct bank, and electrical and telecommunication utilities. Some of this work will be completed under road and lane closures as described above.


Crews will work to relocate water line on Ferguson Avenue, Lyman Avenue, and Morse Place over the next several weeks.


Crews will continue installing stormwater infrastructure between Flynn and Home Avenues. This work will include installing the mainline along Briggs Street and Batchelder Street and the connections to the side streets such as Ferguson Avenue, Lyman Avenue, and Morse Place. Work along Briggs Street will take place outside of the roadway. Work on the installation of the new stormwater treatment system, to be located in the back parking lot of the Flynn Avenue Co-op located at 288 Flynn Avenue, has been postponed. Supplemental information will be shared regarding the schedule of this work as it becomes available.

 

Next week, crews will continue electrical and telecommunications work for residences on Briggs Street, Ferguson, Lyman, and Home Avenues. This work will require service connections to residences over the upcoming weeks. A member of the Champlain Parkway project team has reached out to property owners in advance to schedule service connections. If you have received information regarding these services and have not yet scheduled this work, please reach out the project team or contractor representative using the contact information provided on the flyer.


Crews will continue installing duct bank along Briggs Street and Morse Place throughout next week.


Crews will begin soil remediation work on the southeast corner of Briggs Street and Flynn Avenue within the City’s ROW. This work will include excavating and properly disposing of contaminated soils before backfilling the area with clean materials. Crews will also work on utilities in the area. This work will be completed off the roadway.



Independent utility companies will be onsite over the next several weeks relocating existing utilities. There is the potential for utility service disruptions as part of this work. Impacted businesses and residents will be notified in advance by the independent utility companies. 

PROJECT LOOK AHEAD (JANUARY 16 - 20): 


These activities are anticipated and subject to change as construction conditions dictate.


  • Utility work will continue between Flynn and Home Avenues:
  • Stormwater infrastructure throughout
  • Electrical and telecommunication conduit
  • Duct bank installation
  • Soil remediation on the southeast corner of Briggs Street and Flynn Avenue
  • Independent utility companies will be onsite relocating utilities

PROJECT LOCATION:

The Champlain Parkway Project spans a 2.8-mile area from the I-189 intersection with US 7 to Lakeside Avenue, and includes upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Main Street. 

The initial contract includes the construction of the Champlain Parkway from Home Avenue to Lakeside Avenue, upgrades to Lakeside Avenue, and improvements to the section of Pine Street between Lakeside Avenue and Kilburn Street. 

PROJECTED COMPLETION:

Initial Contract 2024

Final Contract 2027

Project Website

CONTACT US:

For more information about the project please visit the project website champlainparkway.com or contact the project team via the project hotline, 802-496-8956 or by email: info@champlainparkway.com.

Facebook  Twitter