Please provide MoDOT a plan to spend Non-Primary Entitlement (NPE) and COVID funds by Dec. 13. If you are unable to spend these funds, please contact your MoDOT aviation project manager to start the turnback process for NPE. In the next couple of weeks, consultants for each airport will receive an updated email on available expiring funds and include a meeting invitation. This meeting will provide an opportunity to present and discuss each airport's plan for their expiring funds.
Expiring NPE Funds - Need to be expended by:
· 2019 NPE: July 21, 2025
· 2020 NPE: July 30, 2025
· 2021 NPE: Aug. 1, 2025
Expiring COVID funds - Need to be expended by:
· CRRSA: June 16, 2025
· ARPA: Aug. 15, 2025
2022 BIL AIG Funds
BIL AIG 2022 funds will not be extended and will be recovered by the FAA. Please submit the final design cost (if design only) and/or final construction bid cost and/or final construction inspection cost to MoDOT by March 1, 2025.
|