Work continues Saturday to prepare for paving next week


The project contractor will work on Saturday, Nov. 2, to continue roadway grading and miscellaneous drainage work. The contractor plans to complete roadway grading next week and begin paving operations on Wednesday, Nov. 6, weather and other conditions permitting. During the week of Nov. 11, the contractor plans to pave driveway aprons.


The contractor will continue their practice of alerting residents with door notices ahead of their work that may interfere with driveway access.


Full road closures will not be in effect on Election Day, Tuesday, Nov. 5. If any resident is unable to leave their home because of the road construction, please contact Community Services at 603-516-6450.


Two-week project outlook


Saturday, Nov. 2

  • Grading roadway in project area;
  • Miscellaneous drainage work throughout project area;
  • Parking restrictions are in effect during work hours.


Week of Nov. 4

  • Roadway construction on Fifth Street, from Grove to Fourth;
  • Miscellaneous drainage and prep work;
  • Fine grading;
  • Paving;
  • Sidewalk grading;
  • Excavation and installation of duct banks;
  • Parking restrictions are in effect during work hours.



Week of Nov. 11

  • Sidewalk curb installation;
  • Prep and pave driveway aprons;
  • Excavation and installation of duct banks;
  • Parking restrictions are in effect during work hours.


Please note: the schedule is subject to change due to weather and other conditions.


Questions or concerns? Please contact:


Jillian Semprini, City of Dover – Assistant Engineer

603-516-6450 

j.semprini@dover.nh.gov


Hakan Coban, Woodard and Curran – Onsite Resident Project Representative 

978-775-2046

Hakan.Coban@WoodardCurran.com


More information


Find more information about the project at the dedicated project webpage https://www.dover.nh.gov/government/city-operations/community-services/projects/fifth-street-grove-street-reconstruction-project/ or call Community Services at 603-516-6450.


Forwarded this email? To sign up, visit https://bit.ly/dovernewsletters, and add “Project updates: Fifth Street and Grove Street Reconstruction Project” to your current email subscription list.

Facebook  Twitter